PROJECT INFORMATION

Andrew Weil Center for Integrative Medicine

Description

This project will develop a new facility for the Andrew Weil Center for Integrative Medicine (AWCIM) to centralize their operations in a physical building and landscape environment that supports their philosophy of healthy work environments.

Status

Completion of Building Commissioning and Closeout Phase in progress.

Project Number
19-9472
Building Number(s)
233
Current Budget
$23,000,000
Projected Ultimate Budget
$23,000,000
Project Manager
Construction Project Manager
Construction Schedule
May 2022 - March 2024
Contractor
DPR Construction
Phase
Construction
Design Professional
Line and Space, LLC
Delivery Method
CMR
GSF
29,400
VIEW SCHEDULE